Demolition Environmental Enabling Civil Engineering Plant Hire

NIMR Mill Hill

- 17/11/20

Overview

Client: Barratt East London

Value: £2,000,000

Programme: 9 months

Overall recycle percentage: 86%

Description

The animal testing laboratory in Mill Hill was the centre for the testing of all major disease including Ebola and TB. The site was heavily contaminated with asbestos which was removed by ourselves as part of the demolition contract. The remaining buildings were demolished and recycled for re-use. The programme involved a close interface with the follow-on trades which were all managed by Rye as Principal Contractor.